Lincoln Lifestyle Eagle Point moves closer to welcoming residents
Construction continues to advance at Lincoln Lifestyle Eagle Point, with our team building 20 homes and another 15 on order. We anticipate first settlements in February 2027 and aim to complete 35 homes by the end of June.
Homes and infrastructure progress
Our team has completed Stage 1 civil works and home frames and is now installing plumbing and electrical connections. Next, cladding works will begin in November, bringing the homes’ exteriors to life.
Meanwhile, Stage 2 civil works remain on track to reach practical completion in mid-November. We’ve also started the process of connecting permanent power to the estate, with substation delivery scheduled for the end of October. Alongside this, NBN backhaul works are underway to connect the community to the wider network.
To support the community’s electricity needs, we’ve appointed LPE to deliver the estate’s embedded network. Every new home will also include a 4kW solar system.
Clubhouse, landscaping and display home ahead
Looking ahead to November, our team will begin clubhouse construction, landscaping and entry works. Together, these projects will help shape the community’s shared spaces and create a welcoming arrival.
Our display home is also on track to open in December. Once it opens, prospective homeowners can explore the layout, finishes and features firsthand.